Project
Demolition and Installation of Steels
Client
3 Interiors
Location
Ormonde Road, Sheen
Works duration
4 Weeks
Overview
Project breakdown:
- Termination of existing services
- Installation of temporary site power
- Complete strip out back to shell
- Demolition of conservatory
- Strip out of all Mechanical + Electrical
- Removal of ceilings
- Clearance and Segregation of all waste, ready to be recycled
- Removal of wall & floor tiles
- Removal of floor coverings
- Removal of ducting
- Removal of window finishes
- Removal of raised flooring
- Removal of all waste on Titan wait & loads
- Installation of new steel work by Titan