Project
Demolishment of Walton Snooker Centre
Client
Walton Snooker Centre
Location
145 Molesey Avenue, West Molesey, KT8 2RY.
Works duration
1 Month
Overview
- Strip out of entire building
- Strip out of all toilet areas
- Strip out of kitchens
- Strip out of all Mechanical + Electrical
- Demolition of side building
- Demolition of rear building
- Demolition of concrete stairs
- Demolition off all internal brick / block walls
- Demolition of all external brick / block walls
- Diamond saw cuts to form openings
- Diamond saw cuts to beams for removal
- Removal of all asbestos & hazardous wastes
- Removal of portal frame roof structure
- Removal of lift
- Removal of furniture
- Removal of ceilings
- Removal of plasterboard partition walls
- Removal of floor coverings
- Removal of wall & floor tiles
- Removal of ducting
- Removal of waste on Titan Roll on Roll off skips
- Removal of all waste on Titan wait&Loads
- Chasing in floor and walls for new services