Walton Snooker Centre

Project

Demolishment of Walton Snooker Centre

Client

Walton Snooker Centre

Location

145 Molesey Avenue, West Molesey, KT8 2RY.

Works duration

1 Month

Overview

  • Strip out of entire building
  • Strip out of all toilet areas
  • Strip out of kitchens
  • Strip out of all Mechanical + Electrical
  • Demolition of side building
  • Demolition of rear building
  • Demolition of concrete stairs
  • Demolition off all internal brick / block walls
  • Demolition of all external brick / block walls
  • Diamond saw cuts to form openings
  • Diamond saw cuts to beams for removal
  • Removal of all asbestos & hazardous wastes
  • Removal of portal frame roof structure
  • Removal of lift
  • Removal of furniture
  • Removal of ceilings
  • Removal of plasterboard partition walls
  • Removal of floor coverings
  • Removal of wall & floor tiles
  • Removal of ducting
  • Removal of waste on Titan Roll on Roll off skips
  • Removal of all waste on Titan wait&Loads
  • Chasing in floor and walls for new services

When a job’s too big for just any old London demolition company, you need Titans to do it right.

CONTACT US

Accreditations